Șeful CNAIR, anunță că lucrările pe lotul 1 al A0 Nord au ajuns la un stadiu fizic de 82%

Cristian Pistol, the director of CNAIR, announced that construction on the A0 Nord highway lot 1 is 82% complete, with 780 workers and over 370 machines on site. Ongoing work includes asphalt laying, service area construction, and installation of safety features. The completion of this 17.5 km section is targeted for the end of this year, but weather conditions may affect the timeline. Realistically, full connections to DN1A and DN7 may not be ready until 2026, while the A1 connection is expected to be completed by April 2027. The project is funded through the Transport Program 2021-2027, with a contract value of 815.07 million lei.