Șeful CE Oltenia spune că menținerea în viață a grupului 5 de la Turceni este esențială pentru securitatea energetică a țării . Grupul este însă oprit de două zile în urma unei avarii, cu cazanul spart - Economica.net

The operation of Unit 5 at Turceni Power Plant highlights the importance of Complexul Energetic Oltenia (CEO) for Romania's energy security. Although currently offline due to a malfunction, it is set to restart on September 7. The Romanian government has approved a memorandum to maintain lignite-based energy production capacities, extending operational timelines for Turceni and Craiova plants beyond previous commitments. This decision aims to ensure stability in the national energy system, especially during low renewable energy production periods. CEO's leadership emphasizes the significance of this unit for both the company and local communities, despite facing potential EU penalties for delayed closures.