Se vede deja asfaltul pe autostrada dintre Sibiu și Făgăraș / Lucrările se apropie de 50% / Ar trebui finalizată în mai 2028
The construction of the highway section between Arpașu de Jos and Sâmbăta de Sus is progressing steadily, with 48% completion reported. The Turkish contractor Makyol has made significant advancements in earthworks and foundation laying. The project, which began on December 2, 2024, is expected to be completed by May 2, 2028, with a total cost of 1.773 billion lei. This section will connect with other highway segments in the region, enhancing transportation links.