Se lucrează în ritm alert la lotul Joseni-Ditrău din Autostrada Unirii. S-au făcut deja 12% din lucrări într-o lună și jumătate
Construction on the Joseni-Ditrău section of the Unirii Highway is progressing rapidly, with 12% completion in just a month and a half. Over 300 workers and 240 machines are actively engaged in various tasks, including the completion of 400 out of 600 beams. The project spans 14.4 km and includes 18 bridges and passages, with a 24-month deadline for completion. Additionally, two wildlife crossings are being built to ensure safe animal passage. The project utilizes advanced BEEM technology for efficient management and problem identification.