Se închide una dintre marile „găuri” de pe A1: Margina–Holdea a ajuns la 70 la sută / foto
Significant progress has been made on the Margina-Holdea section of the A1 motorway, reaching about 70% completion. Key advancements include the installation of beams and preparation of decks at various bridges and viaducts. All 64 beams have been installed at the first bridge near Margina, while the longest bridge at kilometer 52+150 is 65% complete with 82 of 208 beams installed. The viaduct between tunnels has all 24 beams in place, and work continues on the superstructure. Future tasks include reinforcing, formwork, and concrete pouring for the decks, followed by road layers and safety elements installation. This section is crucial for the A1 motorway's completion.