Se așterne primul asfalt pe Margina–Holdea: autostradă continuă de la Sibiu la Nădlac, tot mai aproape
The construction of the Margina–Holdea section of the A1 highway is progressing, with 3,000 tons of asphalt already laid and tunnel work advancing. UMB Spedition is working on the base layer and has started producing prefabricated beams for essential structures. The project, valued at 1.82 billion lei, is funded by the National Recovery and Resilience Plan. Completion will connect Sibiu to Nădlac, enhancing transport on a key transit route in Romania.