Șantierul pasajului de la Crișul din Oradea: Constructorii vor să mute toate rețelele până la finalul lunii august (FOTO)

The construction team for the underground passage near Crișul shopping center in Oradea aims to clear the site by the end of August to focus on excavation work. They are currently relocating gas pipelines and electrical networks, with significant progress on the foundation piles. The project, which began on May 22, has a budget of approximately 69 million lei and is expected to last 22 months, with hopes to reopen traffic by autumn 2027.