Poduri, terasamente și 767 de muncitori: stadiul lucrărilor pe tronsoanele 3 și 4 ale A13, Sibiu - Făgăraș / video

The construction of the Sibiu-Făgăraș Highway, particularly section 3, is progressing well, with 44% completion and significant work on bridges. Section 4 is at 27% completion, with ongoing efforts on various structures. The total cost for both sections is approximately 2.96 billion lei, with a completion deadline set for 2028.