Peste 70 km de rețele subterane, modernizate odată cu liniile de tramvai. „Planul de pe hârtie contravine realității din teren”

In Bucharest, over 70 kilometers of underground networks are being modernized alongside tram line works, facing challenges due to discrepancies between planned and actual pipe locations. The complexity arises when underground utilities do not match the documentation, leading to project delays and the need for new plans. The mayor emphasizes the importance of simultaneous modernization to prevent future infrastructure issues. Weather conditions also impact progress, causing temporary work stoppages. Despite delays, workers are reassigned to other areas until solutions are found.