Peste 50% pe unul dintre tronsoanele Autostrăzii Sibiu - Făgăraș. Cum avansează lucrările pe A13
Construction on the first two sections of the Sibiu - Făgăraș Highway (A13) is progressing, with the segment between Avrig and Arpașu de Jos exceeding 50% completion. The Boița – Avrig section is at 23.54% completion. The second section employs 430 workers and 340 machines, with doubled mobilization since summer. Work includes earthworks, foundations, and drainage systems. The first section has 648 workers and focuses on earthworks and hydrotechnical structures. The total value of contracts for both sections is 3.43 billion lei, funded by the Transport Program 2021-2027. The entire highway will span 68 kilometers and is expected to be completed by 2028.