Nici în acest an ieșenii nu vor circula pe autostradă. A7 avansează spre Pașcani, în timp ce pe A8 lucrările întârzie

Iasi County will not have any operational highway this year, as the A7 progresses while the A8 faces delays. The A8 construction is stalled, with only preliminary work done near Pascani. The Moțca-Târgu Neamț section of A8 started in February 2025 but is currently halted. Resources have shifted to the A7 project, prioritized for PNRR deadlines. The Moțca-Târgu Neamț lot was moved to the 2021-2027 Transport Program, which is over-contracted. Other A8 sections in Iasi are also delayed due to legal challenges.