Lucrările pe șantierul Variantei de Ocolire Timișoara Vest au ajuns la aproape 20%
Construction progresses on the Timișoara West Bypass, with significant advancements in various areas. The project spans approximately 14 km and includes two lanes in each direction along with four grade-separated interchanges. Work on the roadbed involves filling, soil stabilization, and the installation of successive layers, including reinforced ballast. Over 75% of the concrete piles have been completed, and production of prefabricated beams is ongoing. Nearly 90% of the foundations for the culverts are done, with more than 50% of the prefabricated elements installed. Overall progress is nearing 20% four months after the start order was issued.