Lucrările de modernizare a infrastructurii feroviare din Portul Constanţa au ajuns la 89%, în etapa I. Imagini noi de pe şantier

The modernization of the railway infrastructure at the Port of Constanța is progressing, with 89% completion in Phase I and 13% in Phase II. The first phase focuses on electrification and safety improvements, while the second phase has a budget exceeding 500 million lei. The project aims to enhance transport capacity and safety for freight trains. The contractor for both phases is Bawi Construction S.R.L. and Swietelsky S.R.L. Significant work has been completed, including the installation of railway superstructure and drainage systems. Funding comes from the Connecting Europe Facility and other sources.