Încălzire mai ieftină cu 50% / Sistemul geotermal devine funcțional la Pecica / Un proiect întârziat cu 3 ani / La Sântana, lucrările vr fi finalizate în 2028
The geothermal heating system in Pecica will serve 13 public buildings this winter after a three-year delay. In Sântana, the project is only 55% complete, with a new deadline set for 2028. The Pecica project, valued at around 25 million lei, faced delays due to technical changes and component delivery issues. The new system is expected to reduce heating costs by about 50%. In Sântana, the similar project is also delayed due to misunderstandings between the contracting companies, with only part of the necessary infrastructure completed.