Imagini în premieră, din avion, cu "perla coroanei" de pe A3. Cum arată șantierul pe sectorul Nușfalău - Poarta Sălajului
Recent aerial images shared by Pro Infrastructura showcase the construction site of the most expensive highway segment in Romania, the A3 between Nușfalău and Poarta Sălajului. Preparatory work has commenced on the 41-kilometer stretch, which includes the Meseș tunnel. Currently, activities focus on archaeological excavations and site organization, with significant mobilization noted in Crasna. The project is still in the design phase, with construction permits expected by late 2026. The contract, signed in April 2025, is valued at 6.62 billion lei and includes a 2.89-kilometer tunnel, the longest in Romania. The project aims for completion by the end of 2031, following a decade of delays and previous failed tenders.