The Turceni power plant's Group 5 has faced an accidental shutdown due to a boiler explosion, requiring 48 hours for repairs. Following this, scheduled maintenance will take three weeks. The incident was caused by erosion of the boiler walls, leading to cracks and an explosion, but no injuries occurred. The plant's director highlighted the need for regular maintenance and the challenges posed by the lack of an alternative steam-generating unit. Repairs will depend on the assessment of damaged pipes, and legal exemptions are necessary for restarting operations in emergencies. The plant employs 530 staff, with 120 available for repairs.