GALERIE FOTO Progres de 70% la ”ciotul” Margina – Holdea din autostrada Sibiu - Nădlac / Echipele accelerează montarea grinzilor și turnarea plăcilor de suprabetonare
The construction progress on the Margina – Holdea section of the A1 Highway has reached about 70%, with significant advancements in the installation of prefabricated elements. All 64 beams have been installed at the first overpass, and 82 out of 208 beams are in place at the longest overpass. Work continues on the viaducts, with all necessary beams installed at some locations. Upcoming tasks include finalizing the deck and ensuring road safety features are in place.