GALERIE FOTO Progres de 70% la ”ciotul” Margina – Holdea din autostrada Sibiu - Pitești / Echipele accelerează montarea grinzilor și turnarea plăcilor de suprabetonare

The construction progress on the Margina – Holdea section of the A1 Highway has reached about 70%, with significant advancements in the assembly of prefabricated elements. All 64 beams have been installed at the first overpass, and 82 out of 208 beams are in place at the longest overpass. The viaduct between the two tunnels has all 24 beams installed, while work continues on the viaduct at kilometer 55+775. Future tasks include finalizing the deck and installing road safety elements.