FOTO Traficul sub Podul Constanța va fi redeschis la două benzi/sens luna viitoare. Anunțul PMB despre lucrările la linia de tramvai - Economica.net
The Bucharest City Hall anticipates that the tram line works at Podul Constanța will be completed next month, ahead of the 2027 deadline. Additionally, expansion works for the underpass may begin in 2028. Lot 4, covering nearly 8 km, is progressing well, with the site expected to close around October 15. The contractor has been working diligently, including weekends, to expedite the project. Recent activities include installing tracks and preparing for concrete and asphalt layers. The expansion of the underpass will require feasibility studies and expropriations, with construction expected to start in 2028.