FOTO | Explicațiile primarului Ciucu pentru dispariția misterioasă a muncitorilor de pe zecile de șantiere din București: sunt prinși în „hățișul” de țevi din subteran • Știri București
Bucharest's municipality clarified the lack of visible work at tramway construction sites, attributing delays to underground utility complexities and archaeological finds. The city is modernizing both tram tracks and over 70 kilometers of underground networks, revealing discrepancies between official maps and actual underground conditions. Weather also affects progress, with heavy rain causing work stoppages. Mayor Ciprian Ciucu emphasized the importance of thorough underground work to avoid future issues, while previously citing contractor payment delays as a reason for inactivity. This highlights the challenges faced in urban infrastructure projects.