FOTO Autostrada A1 Sibiu - Pitești: Ce progrese au mai făcut turcii de la Mapa - Cengiz la tunelurile Balota și Robești - Economica.net
The Regional Directorate of Roads and Bridges (DRDP) Craiova provides updates on the A1 Sibiu-Pitești highway construction, focusing on the Balota and Robești tunnels. The Balota tunnel is 500 meters long, with partial excavation completed, while the Robești tunnel, 866 meters long, has finished excavation on one side and is progressing on the other. The Boița-Cornetu section is technically complex, featuring multiple tunnels, bridges, and viaducts. This highway is crucial for both Romania and the EU, with a contract value of 4.25 billion lei and a duration of 68 months.