FOTO | Autostrada A0 Nord: Lotul 3 Afumați – Pantelimon a ajuns la 91,5% execuție

Construction on Lot 3 of the A0 North Highway is 91.5% complete, with authorities aiming for traffic opening by the end of September. The critical point is the DN3 overpass, which must be finished for the entire lot to be operational. Recent inspections show increased mobilization from the contractor, with significant progress on various structures. The project, valued at nearly 398 million lei, is co-financed by European funds and will connect key highways, alleviating transit traffic in northern Bucharest.