EXCLUSIV | CNAIR pierde procesul cu bulgarii pentru penalități de 43 mil. lei

The National Company for Road Infrastructure Administration (CNAIR) lost a court case regarding penalties of 43 million lei against a Bulgarian contractor for a section of the A7 highway. The Bucharest Court of Appeal rejected CNAIR's request to annul an arbitration measure related to these penalties. This decision is not final and can be appealed within 15 days. The penalties were imposed due to delays and technical non-conformities in the construction of the highway section. The contractor disputes these claims and seeks an extension of the contract duration, citing additional works and adverse weather conditions. The arbitration process will determine the final outcome of the dispute.