ESENȚIAL | Scenariu de Crăciun: Autostrada Bucureștiului, inel complet în decembrie. CNAIR: Antreprenorul face eforturi ca Lotul 1 al A0 Nord să fie gata anul acesta • Infrastructură București
The A0 Bucharest Highway is nearing completion, with Lot 1 at 82% progress. The opening is highly anticipated by drivers. Three lots are still under construction, with completion of Lot 3 crucial for traffic flow. The contractor aims to open traffic by December 2026, despite a contractual deadline of April 2027. Recent site visits show significant progress, including asphalt laying on key ramps. Lot 3 is being built by a Chinese company, while Lot 4 is managed by a Romanian firm, featuring major structures. Funding for these projects comes from national and European sources.