Două oferte pentru punerea în siguranță a „Podului Tuborg” de pe DN3

The National Company for Road Infrastructure Administration (CNAIR) has received two bids for the safety works of the Tuborg Bridge on DN3. The project, launched in June 2026, has an estimated value between 7.69 million and 10.34 million lei, excluding VAT. The first bid is from GDO MOV IMPEX SRL and PROCONTRANS.CAI FERATE, while the second is from CROBO STONE and MARISTAR COM, with RUTIER CONEX XXI as a subcontractor. The contract includes design and execution phases, with a total duration of 25 months. Traffic restrictions may apply during construction, which is expected to take about 11 months. The bridge is crucial for connecting Bucharest and surrounding areas, and past incidents have highlighted its importance.