Document: Teren cumpărat de 16 ori mai scump din banii Nuclearelectrica / Cum a fost „evaporată” protecția statului în proiectul SMR / Raportul Corpului de Control al Premierului

An investigation by the Prime Minister's Control Body reveals irregularities in the land sale for the Doicești nuclear project, highlighting significant financial discrepancies and lack of transparency. Nova Power & Gas sold land to RoPower at an inflated price, raising concerns about public interest protection. The report indicates that Nuclearelectrica financed the acquisition through loans, while Nova's contribution was minimal, leading to an unequal distribution of risks and benefits. The findings suggest that the partnership lacked a logical economic justification, with the private partner benefiting disproportionately from public funds.