DN71 Bâldana – Târgoviște: Primii 3 km cu patru benzi, în asfaltare
The modernization of DN71 Bâldana – Târgoviște is progressing on a 3-kilometer stretch, with asphalt work underway. This project, part of a larger 44.13-kilometer upgrade, faces significant delays and scrutiny from the Ministry of Transport's Control Body. Completion for this section is set for March 1, 2027, while the Târgoviște – Sinaia segment is only 1.40% complete, with a deadline of July 10, 2028. Issues such as blocked access for residents and unrelocated utilities have raised concerns among locals. The project, valued at approximately 1.16 billion lei, aims to widen the road to four lanes, but has faced criticism for its execution and planning.