Croații de la Enna cer împrumut BERD pentru un parc hibrid la Mihăilești

Enna Solar plans to secure a loan from EBRD for a hybrid renewable energy project in Mihăilești, Romania, featuring a 87.5 MW solar plant and a 70 MW battery storage system. The project, with an investment exceeding 80 million euros, marks Enna Group's first major investment outside Croatia. Construction began in December 2025, with the plant expected to start operations in Q1 2027. ENEVO Group is responsible for the project's implementation, while Bureau Veritas oversees quality control and compliance with standards.