Cristian Pistol: Lucrările avansează pe Autostrada Sibiu-Făgăraș. Lotul Avrig-Arpașu de Jos a ajuns la 40%

Construction on the first two sections of the A13 Sibiu-Făgăraș highway is progressing well, with over 800 workers and 400 machines on site. The first section, Boița-Avrig, is 17.19% complete, while the second section, Avrig-Arpașu de Jos, is about 40% finished. The total value of contracts for both sections is 3.43 billion lei, funded through the Transport Program 2021-2027. The highway will span 68 kilometers, providing a fast road connection between Sibiu and Brașov, expected to be completed by 2028.