Compania Naţională de Investiţii anunță că lucrările avansează în toate zonele pe şantierul Stadionului 'Nicolae Dobrin' din Piteşti

The National Investment Company reports significant progress at the Nicolae Dobrin Stadium in Pitești, with nearly complete structural work. The North Stand has 99% of its pillars completed, while the East Stand's foundations are finished and pillar work is at 96%. Ongoing work includes parking and foundation areas, revealing the stadium's future dimensions. The venue will seat 15,200 and be the first in Romania to operate entirely on green energy during events. The project, funded by the Ministry of Development and the Pitești City Hall, aims to provide modern facilities for athletes and spectators.