CNAIR transmite că nu a pierdut dreptul la penalitățile de 43 milioane de lei pentru lotul 2 al A7

CNAIR asserts it has not lost the right to 43 million lei penalties against a Bulgarian contractor for delays on the A7 highway. The contractor has contested these penalties, delaying payment until arbitration concludes. A recent court ruling did not annul the penalties or determine the completion status of the works. CNAIR maintains that the contractual deadline was exceeded and will continue to defend its position in arbitration.