CNAIR cere bani de la Guvern pentru a continua lucrările pe lotul 1 al tronsonului Bacău–Pașcani de pe A7. Nu mai e finanţat prin PNRR

Cristian Pistol, head of CNAIR, reported that the first lot of the Bacău – Pașcani Highway is nearing 70% completion, with funding through PNRR until August 31, 2026. Remaining work requires state budget allocation, which CNAIR has requested. UMB is actively working with 500 workers and 350 machines to finish the 30.3 km section this year. Current tasks include road structure, bridge construction, ITS installation, and road marking. The completion of this section depends on securing funding and weather conditions. The contract value is 1.638 billion lei (excluding VAT).