CNAIR anunță că Varianta de Ocolire Timişoara Vest a ajuns la un stadiu general de execuţie a lucrărilor de circa 20%

The construction of the Timișoara West Bypass is progressing, with about 20% completion four months after the start order. The project spans approximately 14 km and includes two lanes in each direction and four grade-separated interchanges. NUROL İnşaat is responsible for the construction, with significant work done on earthworks, structures, and prefabricated elements. The project, costing 1.41 billion lei, is funded through the Transport Program 2021-2027 and is expected to be completed by early 2028.