Centura Azuga-Bușteni: Lucrările avansează, au fost montate grinzile Podului nr. 5. Cum arată noul drum și când va fi gata
The construction of the Azuga–Bușteni bypass is progressing, with the installation of prefabricated beams for Bridge No. 5 completed. Each beam measures 40.9 meters and weighs 86 tons. This project aims to alleviate traffic on DN1 and improve circulation in the Prahova Valley. The bypass spans 7.16 km, divided into two sections, and is part of a larger road infrastructure initiative. Although the initial completion timeline was set for three years, current progress stands at 16%, with further expropriations and authorizations needed. Approximately 250 workers and 70 machines are currently engaged in various construction activities.