Cel mai mare supercomputer A.I. din Marea Britanie este amânat
The UK's largest planned AI supercomputer in Loughton faces significant delays due to energy supply issues, pushing its operational date to the 2030s. The project requires up to 90 MW of power, equivalent to the consumption of around 315,000 homes. Nscale, the company behind the data center, is exploring on-site energy production options. This situation reflects broader challenges as 315 data centers await connection to the national grid, highlighting the increasing pressure AI development places on energy infrastructure.