Când vom putea merge numai pe autostradă de la București la Nădlac: A1 mai are 87 de kilometri de construit

The A1 highway in Romania, stretching 578 kilometers, is nearing completion with 491 kilometers finished. Key segments, including the Sibiu-Pitești and Lugoj-Deva sections, are still under construction. A new segment from Tigveni to Curtea de Argeș is expected to open in 2026, bringing the total completed to 500 kilometers. Additional segments, including Margina-Holdea, are projected for completion by 2027, with the entire highway anticipated to be operational by 2028-2029. The A1 serves as a crucial link between Bucharest and the western border with Hungary, featuring complex engineering works such as tunnels and viaducts.