Buşoi (Ministerul Energiei): Trebuie să punem în siguranţă Centrala de la Cernavodă, să o repornim în siguranţă şi nu putem risca să se deterioreze pompele, ar dura luni, poate un an de zile să le înlocuim. Deci nu ne putem juca cu redeschiderea
Cristian Buşoi, Secretary of State in the Ministry of Energy, stated that the restart of the Cernavodă Nuclear Power Plant is uncertain due to low Danube water levels. He emphasized that safety is paramount, as restarting the plant under unsafe conditions could damage pumps, leading to prolonged outages. Current forecasts suggest no significant increase in water levels in the near future, with potential improvements only by late October or early November. The final decision will depend on specialists ensuring all safety parameters are met before any announcement is made, as market reactions must also be considered.