Avarie majoră la Termocentrala Turceni. Singurul grup pe cărbune rămas în funcțiune s-a oprit după spargerea unui cazan

The Turceni Power Plant faces a major outage as its only operational coal unit, Group 5, was shut down due to a broken boiler. This incident significantly reduces coal contributions to the national energy system, risking supply issues during peak consumption hours. While solar energy supports daytime production, challenges arise after sunset when demand increases. Romania's energy system is already strained due to drought impacts on hydroelectric power and reduced wind energy forecasts, leading to increased reliance on imports. The situation is critical as the country approaches its technical import limits, exacerbating existing energy supply challenges.