Autostrada Sibiu–Pitești, frânată de hârtii: constructorii pot lucra doar pe 45% din șantierul Boița–Cornetu
Construction on the Boița–Cornetu section of the Sibiu–Pitești highway is limited to about 45% due to missing environmental approvals and construction permits. CNAIR's director, Cristian Pistol, stated that the necessary documentation has been with ANMAP for two months. The focus remains on sections with existing permits, while the environmental agreement revision is still pending. Despite these challenges, progress continues, with significant advancements in tunnel construction. The Boița 1 tunnel has been fully pierced, and work is ongoing on two other tunnels. The overall physical progress of the section is around 16%.