Autostrada Bucureștiului A0, cea mai așteptată veste: Lotul chinezilor ar putea fi în trafic pe 20 octombrie. Se așterne asfalt pe ultima zonă - Economica.net

The final asphalt layer is being laid on the last section of Lot 3 North of the A0 Bucharest Highway, reaching 97% completion. This project, constructed by a Chinese company, is crucial for connecting localities and is expected to open by October 20. Recent works include hydro-insulation, soundproof panels installation, and safety features. The completion of Lot 3 is essential for the traffic opening of Lot 4, which is already finished.