Autostrada A8: Cum avansează lucrările în județul Harghita

Over 300 workers and 245 machines are engaged in the construction of the 1D Joseni–Ditrău section of the A8 Highway. The project spans 14.4 kilometers and is being executed by a consortium. The contract lasts 34 months, with 10 months for design and 24 for construction. Ongoing works include ground stabilization, earthworks, and the construction of bridges and passages. The project features 18 bridges, passages, and viaducts, along with wildlife crossings. The Joseni–Ditrău section is part of the mountainous area of the A8 Highway, connecting Moldova and Transylvania to the European transport network.