Autostrada A7 Bacău – Pașcani: Lotul 3 a depășit 55% execuție

Construction progress on Lot 3 of the A7 Bacău – Pașcani highway has surpassed 55%, with 350 workers and over 100 machines on site. The project, valued at 1.76 billion lei, is expected to open in early 2027, despite a contractual deadline of December 2026. The key feature is the Pașcani junction, designed to handle high traffic volumes between A7 and A8. Meanwhile, the first two lots are on track for completion by the end of 2026, pending funding and weather conditions. The total length of the highway is approximately 77 km, all constructed by UMB.