www.antena3.ro/actualitate/centura-azuga-busteni-p
The construction of the Azuga-Bușteni Beltway is progressing with the installation of 90-ton, 40-meter beams at one of the bridges. The project includes 16 bridges and two underpasses over a length of 9.4 kilometers, with 16% completion as of early October, and is expected to be finished by early 2028. The president of Prahova County Council emphasized the complexity of the project in a mountainous area and expressed gratitude to the workers for their efforts. He also highlighted the importance of maintaining safety measures and a steady work pace to ensure timely completion of the beltway.