In Bucharest, the modernization of tram tracks has progressed slowly, with only 5.5 km completed in nearly two years. Currently, work is ongoing on 28 streets, and the city plans to start five more construction sites. The project aims to upgrade 50 km of tram lines by December 2029, or risk losing 1.6 billion lei in non-reimbursable funds. The delays are attributed to the complexity of the work, which includes replacing old utility networks. The mayor has urged a faster pace to meet deadlines, with various lots at different stages of completion, some expected to finish as late as 2029.