The construction progress on the 3C2 Chiribiș - Biharia section of the Transylvania Highway has reached 87% completion, ahead of schedule. The contractor, a Romanian association, employs around 300 workers and utilizes over 300 machines. Key milestones include the completion of 27 km of stabilized ballast and the laying of the first asphalt layer on 26.8 km. The project is monitored by the National Company for Road Investments, ensuring quality and adherence to contractual terms. Weather conditions may impact future work pace. The contract is set to be completed by May 20, 2027, with a budget of 785 million lei funded by European sources.