The Turceni Power Plant's Group 5 has resumed operation after repairs following a breakdown last week. This unit is currently the only operational one at the plant. It was taken offline on October 27 due to a malfunction in the boiler. The group faced multiple outages in recent months, primarily due to boiler issues. The plant, part of the Oltenia Energy Complex, has been gradually reducing its production capacity. The government has decided to keep Group 5 operational until the end of Q1 2028 to ensure energy supply stability.