CNAIR announced that traffic on Lot 3 of the A0 Nord Highway will open only after all safety works are completed. Currently, teams are installing protective barriers and road markings. The construction is nearly finished, with a physical completion rate of about 98.35%. The opening was postponed from the initially scheduled date of October 26, with potential traffic allowed by the end of the year. The project, valued at approximately 398 million lei, spans 8.6 kilometers between Afumați and Pantelimon.