www.oradesibiu.ro/2026/10/28/birocratia-tine-pe-lo
Construction on the mountainous sections of the Sibiu-Pitești Highway is limited due to pending environmental agreements. The next steps depend on regional analyses and CNAIR documentation completion. ANMAP has requested environmental assessments from counties involved, while CNAIR submitted solutions to public concerns. The revised environmental agreement is crucial for full construction operations, as current work is restricted to 45% for section 2 and 30% for section 3. The project aims to enhance connectivity along the Pan-European Corridor 4.