www.stiripesurse.ro/aga-nuclearelectrica-a-aprobat
The Extraordinary General Meeting of Nuclearelectrica's shareholders approved an €800 million loan from the European Investment Bank for the modernization of Unit 1 at Cernavodă. This financing aims to extend the operational life of the unit by 30 years. The loan will be structured in two contracts of €400 million each, with a 22-year maturity and a four-year grace period for principal repayment. The financing is contingent upon a state guarantee for 80% of the principal. Additionally, the meeting addressed the SMR Doicești project and approved measures for RoPower Nuclear's activities. The Ordinary General Meeting initiated the selection process for five board positions.