economedia.ro/foto-prelungirea-ghencea-cand-vor-fi

The Bucharest City Hall has outlined the completion timelines for various sections of the Ghencea Extension project. Tram line works are expected to finish between March and April 2028, with significant upgrades including automated switches and new platforms. Road and sidewalk improvements are scheduled for July to August 2028, following the tram line completion. Other phases include the tram line infrastructure starting in early 2027 and various roadworks planned for late 2027. The project also includes bicycle lanes and retention basins, with overall completion anticipated by September 2028.